Skip to main content
Projects

Toynbee Road, Eastleigh

  • Client
    Foreman Homes
  • Location
    Eastleigh, Hampshire
  • No. of Units
    22 units
  • Residential Properties

Project Overview

Located on the former Jewson depot site in the heart of Eastleigh, this transformative project saw the delivery of 22 piled raft foundations for a new development comprising 105 contemporary homes. Commissioned by Foreman Homes in partnership with VIVID, the project includes a diverse mix of 1- and 2-bedroom apartments, 2-bedroom terraced houses, and 3- and 4-bedroom townhouses, arranged over three storeys.

SPEEDECK was engaged to design and install a combination of voided and non-voided piled raft solutions spanning 3,640m².

The project was successfully delivered within a 13-week programme, beginning in mid-March and completing by the end of April. The work marks a key stage in transforming this brownfield site into a vibrant residential community with landscaped open space and associated parking.

  • 35% concepting
  • 35% detailed design
  • 30% duration on site.
Time Spent Data
Image - Toynbee Road, Eastleigh

Concept Design

The site presented challenging and varied ground conditions typical of brownfield redevelopment. The Made Ground on-site is highly variable, consisting of a mix of clay, silt, sand, and gravel between 0.2m and 4m thick. Over most of the site, this Made Ground constitutes the majority of the potential heave zone.

Beneath this layer lie the River Terrace Deposits, predominantly composed of sandy gravel with limited clay presence. Given the predominantly granular and man-made fill materials, ground heave risk was evaluated as minimal, except in one area of the site where medium volume change potential clay was found to underlay some plots.

This complex geotechnical context required a carefully tailored design approach, balancing structural requirements with the unique subsurface profile to ensure foundation integrity, cost efficiency and long-term performance.

Image – Toynbee Road, Eastleigh
Image – Toynbee Road, Eastleigh
Image – Toynbee Road, Eastleigh

Design Engineering

SPEEDECK’s design team developed a SFA piled raft foundation system to provide a stable foundation for the residential structures.

Additional design constraints for temporary works were put in place due to the proximity of Network Rail Assets. SPEEDECK took the lead on closing these items out working collaboratively with the client.

Image – Toynbee Road, Eastleigh
Image – Toynbee Road, Eastleigh
Image – Toynbee Road, Eastleigh

Construction

Construction works commenced in mid-March and concluded at the end of April, comfortably within the 13-week schedule. SPEEDECK’s scope of works included:

  • Full setting out of SPEEDECK works
  • Installation of a concrete working surface to facilitate raft construction
  • CFA bearing pile design and installation
  • Pile attendance and breakdown, including integrity testing
  • Installation of under-slab drainage and service ducts
  • Shuttering, steel fixing, and concrete placement for all 22 raft foundations
  • Concrete pouring and shutter striking

The team’s integrated delivery model and specialist expertise enabled the smooth execution of works under demanding site and ground conditions. Final inspections and quality assurance were completed as scheduled, marking the successful handover of a critical construction phase.

SPEEDECK successfully delivered a complete piled raft foundation system for 22 plots, part of the 105 new homes at Toynbee Road, Eastleigh. Despite complex ground conditions, the team’s geotechnically informed approach ensured that stability, safety, and buildability were maintained throughout the programme.

The project stands as a strong example of how expert-led foundation engineering can drive efficient, cost-effective outcomes on brownfield regeneration schemes. With foundations complete, the development moves closer to welcoming residents into a new, thoughtfully designed community in the heart of Eastleigh.