Holbrook Park, Snelsmoor

  • Client
    Bellway Homes Ltd East Midlands
  • Location
    Snelsmoor, Derbyshire
  • No. of Units
    Over 200 units
  • Residential Properties

Project Overview

Holbrook Park is part of the wider Snelsmoor Village project, a major residential development delivering up to 800 new homes and a country park on the southern edge of Derby. Developed by Bellway Homes East Midlands, Holbrook Park features a mix of 2, 3, and 4-bedroom properties tailored to modern living.

Work on site began in August 2024, and the first phase was completed by November. Phase two followed shortly after, and work continues for further ongoing phases throughout 2025. In total, the project will include more than 200 piled raft foundations, each designed and built to provide long-term durability and resilience.

  • 30% concepting
  • 35% detailed design
  • 35% duration on site.
Time Spent Data
Holbrook-Park-Key-Plan
Ready to break ground at Holbrook Park with SPEEDECK
Site ready at Holbrook Park for Bellway Homes

Concept Design

The vision behind Holbrook Park is to create a future-ready, sustainable community. Developed by Bellway Homes East Midlands, the scheme brings together smart, energy-efficient homes with forward-thinking design features like air source heat pumps, EV charging infrastructure, and optimised internal layouts for lower energy use. This approach reflects a broader commitment to sustainable placemaking, building not just homes, but resilient, environmentally responsible neighbourhoods.

SPEEDECK played a key role in aligning the structural design of the foundations with this low-carbon vision. Our piled raft foundation solution was chosen not only for its technical performance in difficult ground, but also for its sustainability credentials. Compared to traditional deep trench or strip foundations, piled raft designs require less excavation, less spoil removal, and less concrete and steel overall, reducing both the embodied carbon of the works and the environmental footprint of the build.

With more than 200 foundations designed and installed as part of the scheme, our approach supports Holbrook Park’s broader ambition: to build better, greener homes for the future, starting from the ground up.

Concrete Blinding with SPEEDECK and Bellway Homes
Fresh Concrete Blinding from SPEEDECK Foundations
Ready to pile at Holbrook Park with SPEEDECK
Piling at Holbrook Park for SPEEDECK Foundations
Holbrook Park Bellway Homes Ltd East Midlands SPEEDECK Foundations Piling

Design Engineering

The site presented several geotechnical challenges. Ground investigations revealed Made Ground overlaying layers of clay, sand, gravel, and deeper mudstone and sandstone. Additionally, parts of the site were soft, waterlogged, and subject to shallow groundwater conditions, with the lowest groundwater strike recorded at just 0.5m below ground level.

To address these conditions, SPEEDECK engineered over 200 non-voided piled raft foundations and 12 garage bases using a robust design tailored to the local ground profile.

Our design approach allowed for cost-effective, site-specific solutions that met the client’s need for speed, stability, and long-term reliability.

Piling with Bellway Homes and SPEEDECK
Stepped REBAR with SPEEDECK Foundations
Holbrook Park Bellway Homes Ltd East Midlands Steel fixing
Ground bearing raft from SPEEDECK Foundations for Bellway Homes
Holbrook Park Bellway Homes Ltd East Midlands Piled Raft Foundations with speedeck
Holbrook Park Bellway Homes Ltd East Midlands Shuttering

Construction

Despite a freezing and frosty start to the year, construction at Holbrook Park has progressed efficiently and remains on schedule, with all programmed works completed on time across every phase so far.

The ground conditions on site were challenging at times, particularly due to varying soil strength and weather exposure. To mitigate this, our team worked closely with the client to carefully sequence CBR testing and blinding layer installation, ensuring that exposed virgin ground wasn’t left open to the elements for extended periods. This proactive approach helped maintain ground integrity and avoided unnecessary rework or delays.

Site access also posed some difficulties, especially in areas where roads hadn’t yet been tarmacked, making it hard to reach specific plots with mobile boom pumps. In response, a joint plan was developed to crush and stone up key access routes, allowing for the efficient delivery of materials and equipment. These stoned areas, including some future driveways, were then reused by the client, creating both construction and commercial value for the project.

Quality across the board has remained consistently high, with no issues reported, and our fast-paced delivery continues to support the smooth and timely build out of this major residential scheme.

Holbrook Park represents a successful collaboration between SPEEDECK and Bellway Homes, combining thoughtful design with technical expertise to deliver strong, sustainable foundations for the homes of tomorrow. Our solutions have overcome complex ground conditions and supported the wider vision of building smarter, greener communities.

We’re proud to have played a key role in helping shape Holbrook Park into a vibrant and future-ready development for families across Derbyshire.