Initially, the project had been specified to use a granular piling mat with a traditional pile and ground beam solution. However, SPEEDECK proposed an alternative solution with a vastly reduced dig quantities; this meant that less waste needed removal from sites, which in turn lessened the environmental impact caused by waste transport and processing. This revised approach resulted in several advantages:
Simplified Excavation: The need for extensive excavation for the ground beam solution was eliminated.
Reduced Preparatory Work: The concrete blinding solution significantly reduced the preparatory work and muck away associated with a traditional granular piling mat approach.
Minimised Site Storage: The piled raft solution negated the need for site storage for bulk materials used with the precast ground beam method.
Cost Savings: A 37% cost saving was achieved with the non-voided piled raft solution.