Skip to main content
Projects

Arundel Road Wilmington

  • Client
    J W Stratton Ltd
  • Location
    Angmering, West Sussex
  • No. of Units
    7 units
  • Residential Properties

Project Overview

SPEEDECK Foundations was engaged to deliver a robust and efficient foundation solution for a development of seven new residential properties at Arundel Road, Wilmington. The site presented variable ground conditions with Lambeth Group clays and significant tree influence zones, requiring careful consideration of heave risk and long-term durability.

  • 25% concepting
  • 45% detailed design
  • 30% duration on site.
Time Spent Data
Image – Arundel Road Wilmington
Image – Arundel Road Wilmington
Image – Arundel Road Wilmington

Concept Design

Working closely with the client, SPEEDECK recommended a piled raft solution as the most economical and technically resilient approach. This eliminated the need for multiple trades typically involved in traditional foundations, streamlining delivery while reducing programme risk and management overhead. The total raft slab area was designed at 653m², with all plots integrated under a single, coordinated scheme.

Image – Arundel Road Wilmington
Image – Arundel Road Wilmington

Design Engineering

The foundation design adopted a 225mm reinforced concrete raft slab supported on 300mm diameter CFA piles, combined with 225mm voidformers to provide protection against ground heave. Engineering analysis demonstrated compliance with Eurocode and warranty provider requirements, giving the client assurance of long-term performance. The pile schedule confirmed safe working loads up to 330kN and pile lengths ranging from 6.5m to 12.0m (rounded to the nearest 0.5m).

Support for the outer skin of brickwork was incorporated via recess toes, ensuring seamless integration between foundations and the superstructure.

Image – Arundel Road Wilmington
Image – Arundel Road Wilmington

Construction

SPEEDECK delivered the complete substructure package, combining piling, slab, and associated works into a single integrated solution, delivered over a 9-week programme. This consolidated approach reduced interface risk, avoided the need for granular piling mats, and ensured programme certainty. By self-delivering the critical substructure works, the team provided a clean, fast, and predictable process from site mobilisation to completion at structural slab level.

The Arundel Road scheme demonstrates the advantages of SPEEDECK’s fully integrated piled raft solution. By combining geotechnical expertise, structural design, and in-house construction capability, the project achieved a technically robust, warranty-compliant outcome. For the client, this meant reduced management burden, certainty of cost and programme, and the confidence of a foundation system designed for lasting performance.