Skip to main content
Projects

Canterbury Road, Westgate

  • Client
    McCarthy Stone
  • Location
    Westgate, Kent
  • No. of Units
    Four-storey apartment units
  • Later Living

Project Overview

McCarthy & Stone appointed SPEEDECK Foundations to design and deliver the substructure works for a new four-storey retirement living development in Westgate, Kent. The site presented variable Made Ground overlying chalk, with soft shallow soils that ruled out traditional strip foundations. The client required a durable, warranty-compliant foundation solution that could support significant structural loads while maintaining programme certainty within a live urban environment.

  • 30% concepting
  • 40% detailed design
  • 30% duration on site.
Time Spent Data
Key Plan at Canterbury Road Kent
Canterbury Road Juliette House McCarthy
Site Ready at Canterbury Road Later Living Development

Concept Design

Following geotechnical review and ground modelling, SPEEDECK proposed a CFA piled raft system to provide consistent bearing across variable strata while minimising excavation. The design integrated the piling and raft slab as one substructure package, reducing trade interfaces and accelerating overall delivery. The solution eliminated the need for deep trench fill foundations, protecting the programme and reducing waste movements on site.

Construction piling for care homes with SPEEDECK 3
Construction piling for care homes with SPEEDECK
Piles in situ for piled raft foundations
Piling with SPEEDECK Foundations 2

Design Engineering

The foundation was designed as a 300 mm reinforced concrete raft supported by 300 mm diameter CFA piles, designed in accordance with Eurocode and warranty standards. Piles achieved a maximum safe working load of 630 kN, with pile lengths ranging from 6.0 m to 14.0 m. The raft, covering a total area of 926 m², incorporated pile caps and localised waterproofing provisions to support lift pits and balcony posts. The ground investigation confirmed the shallow chalk deposits required no heave protection, allowing for a straightforward, non-voided solution.

Concrete pour for piled raft foundation with SPEEDECK and McCarthy Stone 2
Concrete pour for piled raft foundation with SPEEDECK and McCarthy Stone
Lift pit construction for care home development from speedeck
Lift pit construction for care home development from speedeck 2
Finished lift pit construction from SPEEDECK
Piled Raft Construction for Later Living Development 2 (2)
Piled Raft Construction for Later Living Development 2
Piled Raft Construction for Later Living Development 3
Piled Raft Construction for Later Living Development 4
Piled Raft Construction for Later Living Development
Raft construction with SPEEDECK Foundations 2
Raft construction with SPEEDECK Foundations 3
Raft construction with SPEEDECK Foundations 4
Raft construction with SPEEDECK Foundations 5
Raft construction with SPEEDECK Foundations

Construction

SPEEDECK delivered all piling and raft works as a single integrated substructure package, streamlining sequencing for drainage and underslab services. The consolidated scope minimised on-site coordination and provided a safe, clean, and level working platform ready for the superstructure. This efficiency enabled McCarthy & Stone to maintain programme certainty and achieve earlier follow-on access, supporting timely project delivery.

The Canterbury Road project demonstrates how SPEEDECK’s integrated piled raft foundation provides cost certainty, reduced risk, and long-term durability.

By combining geotechnical expertise with in-house design and delivery, SPEEDECK supplied a warranty-compliant and technically robust foundation system perfectly suited to challenging ground conditions and the demands of a multi-storey residential scheme.