Laburnums Care Home Foundations

  • Client
    McCarthy & Stone Retirement Lifestyles Ltd
  • Location
    Westcliff-on-Sea, Southend-on-Sea
  • No. of Units
    1 units
  • Later Living

Project Overview

Laburnums, McCarthy & Stone’s latest Retirement Living development on Chalkwell Avenue, transforms a former derelict nursing home dating back to 1880 into a modern, vibrant community.

The project required a carefully engineered foundation solution to address challenging ground conditions and partial tree influence across the plot.

  • 40% concepting
  • 35% detailed design
  • 25% duration on site.
Time Spent Data
Chalkwell Avenue - Site Plan
Chalkwell Avenue - Key Plan
Chalkwell Avenue - architect drawings
Site Ready at Chalkwell Avenue

Concept Design

The development required a single raft foundation solution to support the Care Home structure. The ground conditions were complex, with Made Ground over River Terrace Deposit (clay, sand, and gravel) above London Clay.

Tree influence and desiccation analysis indicated the southern half of the site would require heave protection, while the northern half, outside tree influence, could be unvoided, offering a more economical solution.

Drainage for foundations 2
Drainage for foundations
Steelwork at Chalkwell Avenue from SPEEDECK

Design Engineering

We engineered a mixed piled raft solution covering a total structural area of 991 m², specifically tailored to the site’s variable ground conditions.

Key design considerations included:

  • Heave protection for clay areas influenced by trees (southern half)
  • Partial non-voided slab design where tree influence was minimal (northern half)
  • Integration with site-specific ground conditions, including Made Ground and River Terrace Deposits

The solution ensured long-term structural stability while optimising material use and cost-efficiency.

Chalkwell Avenue - Piled Raft Construction
Concrete pour at Chalkwell Avenue Care Home
Concrete pour at Chalkwell Avenue Later Living Development
Foundation Construction at Southend on sea
Piled Raft Foundation for Care Home
Piled Raft Foundation for Later Living Developments

Construction

The foundation installation was completed within an 8-week construction programme, delivering the following benefits:

  • Fewer interfaces and trades compared to alternative ground beam solutions
  • Efficient handling of variable ground conditions across the plot
  • Reduced excavation and muck-away volumes
  • Controlled installation of voided and non-voided sections to manage tree-related heave risks

The project progressed smoothly, adhering to programme timelines while maintaining high standards for quality and safety.

The Chalkwell Avenue project demonstrates the flexibility and efficiency of SPEEDECK’s part voided, part non-voided piled raft solution.

By tailoring the foundation design to site-specific ground conditions and tree influence, the project achieved:

  • Optimised cost and material use
  • Robust heave protection where required
  • Swift delivery within an 8-week programme

Laburnums now stands as a modern retirement living development, offering residents high-quality homes with views across Chalkwell Park, supported by a foundation system designed for long-term performance.

 

A very good and efficient system for foundations.

Doug Johnson