Skip to main content
Projects

Eastmere Stables

  • Client
    N.J.S Partnerships Ltd
  • Location
    Chichester, West Sussex
  • No. of Units
    9 units
  • Residential Properties

Project Overview

N.J.S Partnerships Ltd appointed SPEEDECK Foundations Ltd to deliver the substructure works for nine new residential dwellings and detached garages at Eastmere Stables, Eastergate Lane, Chichester. The site presented variable ground conditions with areas of Made Ground, soft Head Deposits and underlying London Clay. The client required a foundation solution that would provide technical robustness and programme certainty while remaining cost-effective across the mixed housing layout. We priced for 1,397m² of structural foundations for 12 x Rafts for 9 Units, 2 x Car
Ports & a double garage.

  • 40% concepting
  • 25% detailed design
  • 35% duration on site.
Time Spent Data
Key Plan Eastmere
Breaking ground at Eastmere Stables with N.J.S Partnerships LTD (2)
Breaking ground at Eastmere Stables with N.J.S Partnerships LTD (3)
Breaking ground at Eastmere Stables with N.J.S Partnerships LTD (4)
Breaking ground at Eastmere Stables with N.J.S Partnerships LTD

Concept Design

Following a detailed geotechnical review, SPEEDECK identified that shallow foundations were not suitable due to the depth and variability of the soft upper soils. A CFA piled raft foundation was therefore proposed as the most efficient solution, integrating both piling and slab within a single substructure package. This approach eliminated deep excavation requirements and avoided the stability risks associated with traditional foundations, offering the client a reliable and streamlined delivery path.

Concrete blinding at Eastmere Stables with N.J.S Partnerships LTD (6)
Concrete blinding at Eastmere Stables with N.J.S Partnerships LTD (7)
Concrete blinding at Eastmere Stables with N.J.S Partnerships LTD (8)
Piling at Eastmere Stables with N.J.S Partnerships and SPEEDECK
Piling machine at Eastmere Stables with N.J.S Partnerships and SPEEDECK

Design Engineering

The site’s ground conditions comprised Made Ground and Topsoil overlying Head Deposits, which in turn sit above the London Clay Formation and Lambeth Group. The upper layers of the Head Deposits were soft sand with intermittent soft clay, making them highly variable and unsuitable for shallow foundations. Reaching a competent soil layer would require excavation of at least 3 meters, approximately 1.7 meters to clear the Made Ground and a further meter to extend beyond the soft Head Deposits, rendering conventional shallow foundations both uneconomic and potentially prone to total and differential settlement beyond tolerable limits.

To address these challenges, a CFA piled raft solution was implemented. This approach combined reinforced concrete raft slabs, 225 mm and 300 mm thick according to structural loading variations, with 300 mm diameter CFA piles designed to Eurocode and warranty standards. Pile lengths ranged from 7.0 m to 12.0 m, achieving a maximum safe working load of 280 kN, while the total raft slab area of 1,397 m² created a unified and durable substructure. The system delivered long-term structural integrity without the need for heave protection, reflecting the non-plastic nature of the soils, and provided an efficient, material-conscious foundation solution that balanced cost, programme, and performance.

Piled raft foundations construction at Eastmere Stables with N.J.S Partnerships and SPEEDECK 14
Piled raft foundations construction at Eastmere Stables with N.J.S Partnerships and SPEEDECK 15
Piled raft foundations construction at Eastmere Stables with N.J.S Partnerships and SPEEDECK 16
Piled raft foundations construction at Eastmere Stables with N.J.S Partnerships and SPEEDECK 18
Piled raft foundations construction at Eastmere Stables with N.J.S Partnerships and SPEEDECK 20
Piled raft foundations construction at Eastmere Stables with N.J.S Partnerships and SPEEDECK 21
Piled raft foundations construction at Eastmere Stables with N.J.S Partnerships and SPEEDECK 22
Piled raft foundations construction at Eastmere Stables with N.J.S Partnerships and SPEEDECK

Construction

SPEEDECK completed the piling and raft construction as a single coordinated scope of substructure works with an eight week construction programme. This integrated approach reduced the need for multiple trade interfaces, simplified sequencing for drainage and services, and ensured early release of plots for follow-on construction. Delivery efficiency was further enhanced through offsite reinforcement preparation and standardised detailing, reducing on-site time and variability.

The Eastmere Stables project demonstrates SPEEDECK’s ability to deliver technically robust and warranty-compliant solutions on sites with challenging ground conditions. The upper soil layers at the site were very soft and highly variable, with Made Ground and Topsoil overlying soft Head Deposits, making shallow foundations both uneconomic and structurally risky.

Recognising these constraints, SPEEDECK was brought in to provide a more efficient and reliable solution. By combining geotechnical expertise with integrated design and in-house construction delivery, SPEEDECK implemented a CFA piled raft foundation system that safeguarded cost, programme, and long-term structural performance. This approach allowed N.J.S Partnerships to proceed with confidence, providing a durable, efficient substructure tailored to the specific challenges of the site.

Guys on site were excellent, all works were completed to a high standard. Would use SPEEDECK again.

Jason Giles