Skip to main content
Projects

Harbourside House, Eastbourne

  • Client
    McCarthy Stone Retirement Lifestyles Ltd
  • Location
    Eastbourne, East Sussex
  • No. of Units
    A four-storey building over one units
  • Later Living

Project Overview

SPEEDECK were appointed to deliver the structural foundations for Harbourside House, a four-storey retirement development in Eastbourne for McCarthy Stone.

The project required the construction of a 1,304m² piled raft foundation slab for the care home building. From the commencement of piling, the programme allowed nine weeks to complete all works, including under-slab drainage and service installations between the piling and slab phases.

The site presented a number of technical and environmental challenges, including variable Made Ground, mixed underlying geology, high UXO risk, CS3 ground gas conditions and a high flood risk location. Despite these constraints, the foundations were successfully delivered within programme.

  • 35% concepting
  • 35% detailed design
  • 30% duration on site.
Time Spent Data
Eastbourne Artists development 2
Site Plan at Eastbourne East Sussex
Eastbourne site ready SPEEDECK

Concept Design

Ground investigation revealed variable and locally deep Made Ground across the site, particularly on the upper platform. Beneath this layer were beach deposits consisting predominantly of dense granular soils, transitioning into soft clay layers and deeper Weald Clay at greater depth.

Given the mixed ground conditions and structural requirements of the building, a piled raft foundation solution was selected to provide a robust and efficient foundation system capable of transferring loads safely through the variable strata.

Additional considerations included:

  • Areas of clay influenced by vegetation, specifically blackthorn, requiring heave protection.
  • High flood risk, potentially affecting final site levels and the ground model.
  • CS3 ground gas classification, requiring appropriate gas protection and ventilation measures.
  • High UXO (Unexploded Ordnance) risk, requiring careful site management during groundworks.
Eastbourne Piling with SPEEDECK
Drainage and Services installation with SPEEDECK 2
Drainage and Services installation with SPEEDECK 3
Drainage and Services installation with SPEEDECK

Design Engineering

The engineering solution incorporated several measures to mitigate the complex site conditions and ensure compliance with environmental and structural requirements.

A HVCP voidformer system was introduced in a small area of the north-east section of the site where clay soils and tree influence posed a potential heave risk.

To address the CS3 gas conditions, the foundation design incorporated an integrated gas protection system, including gas strips and a gas membrane, ensuring the building met the required safety and regulatory standards.

The overall design approach allowed the team to balance structural performance with buildability, ensuring the foundation system could be delivered efficiently while accommodating drainage and service installations between key construction stages.

Eastbourne Foundations with SPEEDECK and Gas Venting
Eastbourne Gas Venting with SPEEDECK
Gas venting foundation preparation with SPEEDECK
Piled raft awaiting concrete pour from SPEEDECK
Piled raft construction at Eastbourne with McCarthy Stone
Concrete pour on later living foundations 2
Concrete pour on later living foundations 3
Concrete pour on later living foundations

Construction

SPEEDECK delivered a fully integrated foundation package, coordinating multiple workstreams to maintain programme efficiency and quality control throughout construction.

The scope of works included:

  • Piling works
  • Concrete blinding
  • Installation of under-slab drainage and services
  • Gas protection measures including gas strips and membrane
  • Formwork and reinforcement installation
  • Lift pit base construction
  • Coordination with warranty provider inspections
  • Concrete pours for the piled raft slab
  • Final strike and site clearance

Despite the challenging ground conditions and logistical constraints, the 1,304m² piled raft slab was successfully completed within the nine-week programme.

The Harbourside House project demonstrates the value of careful planning, technical coordination and experienced delivery when working on complex foundation schemes.

By addressing variable ground conditions, gas protection requirements and environmental constraints through a coordinated engineering and construction approach, Speedeck delivered a robust foundation solution that supports the long-term performance of this retirement living development.

The completed project highlights how an integrated foundation package can help streamline construction programmes while maintaining safety, compliance and build quality.