SPEEDECK aligned our methodical approach with client site pressures to successfully introduce a more streamlined foundation solution.
Concept Design
SPEEDECK enhanced the ground model’s efficiency, resulting in 25% fewer piles than initially anticipated and a streamlined construction process – inline with the rapid development needs of the client.
By eliminating traditional elements like the pile mat, ground beams, substructure brickwork, and beam and block floor, we were able to reduce components and expedite build times.
The incorporation of a concrete raft not only guarantees a robust foundation but also provides a more efficient and seamless construction process.
Provided confidence in the use of CFA piles, aligning with client’s preference and against the popular insistence on Driven Precast Piles.
Understanding the paramount importance of safety and reliability in care home constructions, we provided all-risk coverage on the pile length and structural foundations package.
Design Engineering
SPEEDECK’s confirmed technical and detailed designs aligned with tender allowances, circumventing potential ground obstructions and optimising financial outcomes.
One of the main challenges was the site’s existing piles from its previous use. Our design was able to integrate these structures into the reinforced slab and pile layout without the risk of incurring additional costs.
Initially, the proposed compliant scheme included heave precautions beneath the foundation, but with SPEEDECK’s comprehensive assessment and communication with the warranty provider, these precautions were designed out.
We accelerated turnaround time for drawings allowing for the client’s approval to be secured quickly and efficiently.
Construction
The construction phase was characterised by swift progress and implementation. With a keen focus on durability, quality and speed, SPEEDECK ensured the project progressed seamlessly.
The construction of a waterproof lift pit provided durability and long-term value, backed by a materials guarantee.
SPEEDECK handed over the slab’s first section in just five weeks, and completed the entire reinforced slab in a total of 10 weeks. This marked a 40% increase in speed compared to alternative proposals.