Skip to main content
Projects

Reeds Lane West Sussex

  • Client
    Elivia Homes
  • Location
    Sayers Common, West Sussex
  • No. of Units
    36 units
  • Residential Properties

Project Overview

Elivia Homes appointed SPEEDECK Foundations Ltd to deliver the substructure works for 36 new homes at Reeds Lane, Sayers Common. The development required a foundation system that would provide cost and programme certainty while meeting the technical challenges posed by variable Made Ground, clay soils with potential for heave, and areas of contaminated ground.

  • 25% concepting
  • 45% detailed design
  • 30% duration on site.
Time Spent Data
Image – Reeds Lane West Sussex
Image – Reeds Lane West Sussex
Image – Reeds Lane West Sussex

Concept Design

Following a detailed geotechnical review, SPEEDECK proposed a mixed solution of CFA (continuous flight auger) and pre-cast driven piles supporting a reinforced concrete raft. Driven piles were adopted to non-heave plots, limiting the extent of contaminated soil removal, while CFA piles were required in heave plots to achieve the necessary tension anchorage. This combined approach streamlined delivery, reduced client risk, and avoided unnecessary excavation of contaminated soils.

Image – Reeds Lane West Sussex
Image – Reeds Lane West Sussex
Image – Reeds Lane West Sussex

Design Engineering

The raft design utilised a 300mm thick reinforced concrete slab, selected to minimise pile numbers and reduce the need for excavation of deeper contaminated material. 160mm RDS voidformers were specified beneath plots within tree influence to mitigate heave risk. Piles were designed in accordance with Eurocode standards, achieving a maximum safe working load of 310kN. Pile lengths ranged from 8.0m to 10.0m.

The scheme delivered a total raft slab area of 2,458m². Integration of piling and slab into a single substructure package provided a technically robust, warranty-compliant solution that safeguarded long-term performance.

Image – Reeds Lane West Sussex
Image – Reeds Lane West Sussex
Image – Reeds Lane West Sussex
Image – Reeds Lane West Sussex
Image – Reeds Lane West Sussex

Construction

SPEEDECK delivered all piling, raft construction, and underslab services within an 11-week programme. This included pile installation, voidformer placement, raft construction, reinforcement, and integration of underslab drainage. By combining these elements into one package, client management time was significantly reduced and follow-on trades benefited from a predictable, clean, and safe working platform.

The Reeds Lane project demonstrates how SPEEDECK’s integrated piled raft system provides programme certainty, cost efficiency, and reduced client risk. By consolidating design, engineering, and construction into a single warranty-compliant package, the scheme achieved a fast, streamlined delivery and a durable foundation solution tailored to challenging ground conditions.