Project Overview

Elsea Park is a major residential development for Bellway Homes, forming part of the wider growth of Bourne, Lincolnshire. The scheme delivers 141 new homes designed to meet the growing demand for high-quality housing in the area. SPEEDECK was appointed to provide a fully engineered foundation solution tailored to the site’s variable ground conditions and the influence of surrounding vegetation.

  • 35% concepting
  • 30% detailed design
  • 35% duration on site.
Time Spent Data
Image – Elsea Park, Bourne
Image – Elsea Park, Bourne
Image – Elsea Park, Bourne
Image – Elsea Park, Bourne

Concept Design

The ground investigation identified the presence of Made Ground, underlain by the Kellaways Sand and Clay Member, comprising firm, silty clay with interbedded sand layers. A detailed tree survey also confirmed that all plots sit within zones of potential tree influence, making heave protection a critical design consideration.

Image – Elsea Park, Bourne
Image – Elsea Park, Bourne
Image – Elsea Park, Bourne
Image – Elsea Park, Bourne
Image – Elsea Park, Bourne
Image – Elsea Park, Bourne

Design Engineering

SPEEDECK’s geotechnical and structural engineers developed a robust foundation design incorporating 350mm diameter Continuous Flight Auger (CFA) piles, each embedded 0.5m into the underlying rock strata. The rock profile consisted of a thin siltstone layer over weaker mudstone and strong limestone, requiring careful pile design to ensure long-term stability.

Across the development, more than 1,000 piles were installed, equating to over 7,000 linear metres of piling completed within just nine weeks. In total, the foundation design covered 6,370m² of structural slabs, integrating essential heave protection measures to mitigate the effects of shrink-swell soils and maintain the structural integrity of each plot.

Image – Elsea Park, Bourne
Image – Elsea Park, Bourne
Image – Elsea Park, Bourne
Image – Elsea Park, Bourne
Image – Elsea Park, Bourne

Construction

The construction sequence was carefully managed to maintain programme efficiency and site safety. Across all plots works included:

  1. Installation of the concrete piling mat and working platform
  2. CFA pile installation and testing
  3. Completion of blinding and preparation works
  4. Installation of shuttering and reinforcement
  5. Concrete pouring and completion

The project was delivered to an agreed 13-week programme, with all works completed safely, efficiently, and to specification.

The Elsea Park project demonstrates SPEEDECK’s ability to deliver large-scale residential foundation packages under challenging ground conditions. Through intelligent design, efficient construction, and rigorous quality control, SPEEDECK provided Bellway Homes with a cost-effective, durable, and future-proof solution. The inclusion of heave protection through most of the site ensures long-term performance, safeguarding the development against future soil movement and offering lasting value for both client and end users.