Due to the variable ground conditions, a tailored foundation solution was necessary. Our team proposed a piling approach combined with a mixed voided and non-voided piled raft foundations. This method was selected specifically to manage the expected clay heave and irregular soil composition.
To further streamline the process and improve efficiency, a lightweight piling rig was utilised. This eliminated the need for an engineered piling mat, significantly reducing costs and minimising soil & material movements on site.