Warwick Road, Acocks Green

  • Client
    T R Partnership Homes Limited
  • Location
    Warwick Road, Acocks Green
  • No. of Units
    46 units
  • Residential Properties

Project Overview

T R Partnership Homes  appointed SPEEDECK Foundations to design and deliver the substructure works for a 46-unit residential development at Warwick Road, Acocks Green, Birmingham. The scheme comprises a mix of two-storey houses alongside a four-storey apartment block, requiring a foundation solution capable of accommodating varying load profiles and complex ground conditions. SPEEDECK’s brief was to provide a warranty-compliant system that safeguarded programme certainty while minimising risk and maintaining efficiency across the diverse building layouts. The design approach prioritised a streamlined construction sequence and a robust long-term foundation performance for the client. The project was split into two visits to release the apartments quicker on behalf to Citizen New Homes.

  • 35% concepting
  • 35% detailed design
  • 30% duration on site.
Time Spent Data
Key Plan Warwick Road
Site ready at Warwick Road
Warwick Road, Birmingham - T R Partnership Homes Limited and SPEEDECK Breaking Ground
Concrete blinding ready for Warwick Road Foundations

Concept Design

Following a review of the available geotechnical and structural information, SPEEDECK identified that traditional shallow foundations would present risks due to ground variability and anticipated settlement. A CFA piled raft foundation was therefore recommended as the most technically reliable and efficient solution. By integrating piling and reinforced concrete raft slabs into a single substructure system, the approach simplified construction logistics while reducing the number of trade interfaces. This integrated design strategy enabled consistent load transfer into the underlying strata while maintaining programme reliability across the large residential scheme.

Blinding at Warwick Road, Birmingham - T R Partnership Homes Limited and SPEEDECK Breaking Ground 2
Blinding at Warwick Road, Birmingham - T R Partnership Homes Limited and SPEEDECK Breaking Ground
WarwickRoad Piling for residential Homes
Piling at Warwick Road with SPEEDECK 2
Piling at Warwick Road with SPEEDECK

Design Engineering

The substructure solution incorporated reinforced concrete raft slabs of 225 mm thickness beneath the two-storey housing plots and 300 mm beneath the apartment block, reflecting the differing structural load requirements across the development. Heave protection was incorporated where required, including 160 mm voidformers beneath plots influenced by shrinkable clay conditions, ensuring long-term durability of the foundations. The CFA pile design achieved a maximum safe working load of 490 kN. The development required a total raft slab area of approximately 1,741 m². The engineering strategy balanced structural performance with efficient pile spacing and reinforcement optimisation, delivering a technically robust and warranty-compliant design.

B277DP001 - Plots 1-26 - Warwick Road, Birmingham - T R Partnership Homes Limited
Downstand construction Warwick Road, Birmingham - T R Partnership Homes Limited (2)
Heave protection and piling at Warwick Road
Piled raft construction at Warwick Road with SPEEDECK 2
Piled raft construction at Warwick Road with SPEEDECK 3
Piled raft construction at Warwick Road with SPEEDECK 5
Piled raft construction at Warwick Road with SPEEDECK
Piled raft construction at Warwick Road with step

Construction

SPEEDECK delivered the piling, drainage and raft installation as a single coordinated package of substructure works, significantly simplifying sequencing on site. The site was located deep in a residential area, with logistical and access constraints, so forward planning was essential.

The integrated approach reduced reliance on multiple subcontract trades and facilitated efficient installation of drainage and underslab services. This streamlined construction methodology created a safe and consistent working platform for the superstructure works while maintaining programme certainty across the multi-phase residential development.

The Warwick Road development demonstrates SPEEDECK’s ability to design and deliver efficient piled raft foundations across complex multi-unit residential schemes. Through integrated geotechnical assessment, structural engineering and construction delivery, SPEEDECK provided T R Partnership Homes Limited with a technically robust and warranty-compliant substructure solution that reduced risk, protected programme delivery and ensures long-term structural performance for the development.

Like the SPEEDECK system, very quick and clean.

Steve Gater