Skip to main content
Projects

Barton Park Residential Development (Phase 4A2 & 4B2)

  • Client
    Mostrim Groundworks Ltd
  • Location
    Headington, Oxford
  • No. of Units
    22 x Rafts for 56 units
  • Residential Properties

Project Overview

As part of the wider Barton Park neighbourhood in Oxford, this residential phase by Vistry, comprised a mix of housing and apartment buildings across a large multi-plot development. With varying structural load requirements, multiple building types and a phased construction programme, the project required a foundation solution that could provide both technical certainty and construction efficiency.

SPEEDECK was appointed to review the proposed substructure strategy and develop a solution that would simplify construction, maintain programme momentum and satisfy warranty requirements, while ensuring long-term structural performance across the development.

  • 35% concepting
  • 35% detailed design
  • 30% duration on site.
Time Spent Data
Key Plan Barton Park
Site ready at Barton Park in Oxfordshire
Site ready at Barton Park with SPEEDECK

Concept Design

Following a detailed assessment of the structural proposals and site requirements, SPEEDECK identified an opportunity to move away from a traditional pile-and-ground-beam arrangement in favour of a piled reinforced concrete raft foundation system supported by pre-cast driven piles.

The solution combined the benefits of deep foundations with a structural slab platform, allowing loads from external masonry walls, internal loadbearing walls and floor construction to be distributed efficiently into competent bearing strata. By integrating the piling and slab construction into a single engineered package, the proposed system reduced construction complexity and created a more streamlined route through the substructure phase.

Beyond the structural advantages, the piled raft approach minimised excavation, reduced ground disturbance and simplified sequencing across the multiple plots, helping maintain consistency throughout the development.

Piling at Barton Park
Piling and drainage with SPEEDECK Foundations 2
Piling and drainage with SPEEDECK Foundations
Piled raft construction for Barton Park
Piled raft foundation construction with SPEEDECK Foundations 2
Piled raft foundation construction with SPEEDECK Foundations 3
Piled raft foundation construction with SPEEDECK Foundations

Design Engineering

Reinforced concrete raft slabs ranging from 225mm to 300mm thick were specified, with 160mm voidformers incorporated beneath the slabs to manage potential ground movement. The ground consists of Made Ground / Topsoil over Oxford Clay Formation.

Using a combination of structural loading information, ground investigation data and SPEEDECK’s engineering expertise, the team developed an efficient foundation layout that balanced performance, economy and buildability. Pile lengths were optimised across the site to suit local ground conditions and verified through dynamic and static load testing, providing consistent bearing capacity throughout the development.

In total, the design covered approximately 2,535m² of raft slab construction and delivered safe working pile loads of up to 260kN.

Concrete pour at Barton Park Oxfordshire
Foundations in progress in Oxfordshire with SPEEDECK 2
Foundations in progress in Oxfordshire with SPEEDECK 3
Foundations in progress in Oxfordshire with SPEEDECK 4
Foundations in progress in Oxfordshire with SPEEDECK 5
Foundations in progress in Oxfordshire with SPEEDECK
Heave protection and raft construction at Barton Park

Construction

A key driver for the project was maintaining certainty across a large-scale residential programme. By delivering the piling and raft slab works as a coordinated package, SPEEDECK reduced the number of construction interfaces on site and simplified coordination between trades.

The system also provided a stable working platform for follow-on trades while allowing below-slab drainage and services to be incorporated efficiently, helping the wider construction programme progress with minimal disruption. Completed within a 14 week construction time.

The completed foundation solution provided Mostrim with a robust, NHBC-approved substructure system that balanced technical performance with practical construction benefits. Through the adoption of a piled raft foundation, the project achieved a simplified construction sequence, reduced site complexity and improved programme certainty across a large residential development.

The Barton Park scheme demonstrates how early engineering input and an integrated foundation strategy can unlock efficiencies that extend well beyond the substructure phase, delivering value throughout the build programme.

Craig Ford (Mostrim) - System was really good. The project was programmed and managed really well by Gareth. Would use SPEEDECK again.
Gary Price (Vistry)- All went very well and the guys on site all worked very well. I would use the SPEEDDECK system again.